Living Waters Updates

March 7th, 2024
Philip Brochard Philip Brochard

March 7th, 2024

Construction Finishes - On March 3rd, the Property Committee reviewed HY’s recommended finishes––the tile for the bathrooms, carpet for the undercroft rooms, paint colors, etc.––the most outward face of the construction work. HY was working from the “warm” palette chosen earlier and offered materials with gray, blue, green and terracotta accents. Soon the Property Committee will be conferring with the Kitchen and Undercroft user groups to consider the options. Special consideration is being given to the look and feel of the materials used in the Chapel as a holy space to make sure it offers an inviting interior…

Read More
February 15th, 2024
Philip Brochard Philip Brochard

February 15th, 2024

There has been a flurry of Living Waters administrative action recently. Late last week HY Architects submitted our construction permit application, and an 82-page set of plans, to the City of Berkeley to start the permit process for our Living Waters work!

Read More
January 11th, 2024
Philip Brochard Philip Brochard

January 11th, 2024

Even as we have celebrated Christmas and the New Year, the work of the Living Waters Project has continued!

The Isaiah Project team has been evaluating organizations that could be partners in its effort to heal the breach of racial injustices. The team has identified a handful of organizations to engage with and anticipates beginning conversations with many of them soon.

Our architect, HY, has been developing a comprehensive set…

Read More
December 14, 2023
Emily Hansen Curran Emily Hansen Curran

December 14, 2023

HY Architects continue to refine the design and development for placement of the elevator in the foyer/lift location. Responding to concerns about traffic flow and aesthetics in the Nave, they are currently evaluating an option that would not build a vestibule inside the nave…

Read More